
Since an in-floor Jacuzzi was planned, a slab foundation wouldn't work
because of the Jacuzzi drain. A crawl-space foundation was opted for.
|

Because the land had a gentle slope, the footing was stepped in order
to decrease the amount of digging required for the footing. |

Cinder blocks being added to the completed footing. |

Cinder blocks finished showing load-bearing wall half way back that will
support the front of the hayloft. |

Another view of the completed foundation and our heavy-duty construction
vehicle. |

In order to hold calculated loads, the floor joists were 2x12x14 yellow
pine. |

Jacuzzi arrives. We found it on eBay in Indiana, so we made a road trip out of
picking it up. |

Plywood floor being laid by the Etzel Construction Crew (Ronda, Mitchel,
Ariel, and Sydney). Exterior walls being constructed. |

Innkeeper on left with the Ledbetter Construction Crew (Anna, Rob, Robann,
and Zachary) after completing hayloft floor. |

Trusses were constructed using a homemade jig on the hayloft floor and
then slid into place. |

After weeks and weeks of building trusses, they're finally all up. |

Interior view, from living room, of hayloft and truss works. |

Studs for bathroom (right) and master bedroom (back). |

View from living room of the master bedroom after Jacuzzi spa was installed. |

The Jacuzzi had to go in first as it predicated slope and run of the rest of the sewer pipes and septic system. |

Sheathing goes up on roof and walls. We have a front door!!! |

Siding begins to be installed. |

Siding complete and awaiting installation of trim. |

Barn theme starts to take shape with the installation of trim. |

Wiring and insulation get installed. |

Steps to the hayloft are roughed in to check clearances. |

Septic system getting installed. |

In order to get a more "Amish" look to the flooring, 2x6x14 yellow pine
was milled into 1x6x14 pieces. |

Milled wood laying on the garage floor ready for installation. |